Akela Constructions constructed a storeroom extension to the G Block Hall at Nerang State High School. This was completed in June 2018.

This included the following:

  • All works as per Architect and Engineers certified plans
  • Construction of footing slab layout
  • Construction of roof framing, bracing layout, wall framing and tie-down
  • Site Drainage
  • Removal of two existing downpipes
  • Installation of roof, fascia, downpipes and associated flashings as per Engineers certified plans
  • Installation of external wall sheeting to match existing
  • Install FC sheeting to inside, flush set and paint
  • Provide and install all windows and doors with window and door furniture
  • Provide lights, power points as per drawings
  • Full external and internal paint
  • Removal of roof structure outside staffroom including 5 posts and roof
  • Provide all site fencing and skip to remove rubbish from site